Quantification & Costing of Construction Works Case Study

Quantification & Costing of Construction Works Case Study. Based upon the substructure take-off included with the following documents prepare an abstract and bill of quantities for the works.

Documents

1          Substructure documents and notes

 

2          Substructure take off

 

3          Substructure abstract

 

4          Appendix A guidance.

 

NRM 5 Excavation and filling

 

NRM 11 In-situ concrete works

 

NRM 14 Masonry

 

Key   considerations 1 2 3 4
Preparation   of an abstract for the proposed substructure work        
Preparation   a bill of quantities from the abstract including final quantities, referenced   items of work, page totals and summary page        

 

Part 1 requires the transformation of the take off into the final BQ stage.

Top of Form

Bottom of Form

2) Based upon the drawings for the student accommodation used in unit 3 measure the suspended ceilings to all of the bedroom units excluding any work to the staircases and corridors including the preparation of an abstract and priced bill of quantities based on the specification and rates contained in the next paragraph.

Gyproc M/F suspended ceiling with hangers plugged and screwed to the concrete soffit, 900 x 1800 x 12.5mm tapered edge wallboard infill, joints filled with joint filler and taped to receive direct decoration. Rate £31.01 per m2

Decoration three coats emulsion paint. Rate £4.54 per m2

25 x 40mm softwood shadow gap to perimeters. Rate £3.80 per m

Decoration two coats black stain to exposed surface. £1.93 per m

  1. Sample take off paper and NRM for suspended ceilings and decorations included in reading material.
Key   considerations 1 2 3 4
Detailed   measurement of the required work        
Calculations   of relevant areas and lengths including abstract of items        
Preparation   a bill of quantities from the abstract including final quantities, referenced   items of work and page total        

 

Part 2 requires the proposed suspended ceiling works to be measured, abstracted, billed and priced.

Documents and drawings

5  Take off paper

NRM 29 Decoration

NRM 30 Suspended ceilings

100B Lower Ground Floor

101D Ground Floor

102D First Floor

103D Second Floor

104D Third Floor

105D Fourth Floor