Quantification & Costing of Construction Works Case Study
Quantification & Costing of Construction Works Case Study. Based upon the substructure take-off included with the following documents prepare an abstract and bill of quantities for the works.
Documents
1 Substructure documents and notes
2 Substructure take off
3 Substructure abstract
4 Appendix A guidance.
NRM 5 Excavation and filling
NRM 11 In-situ concrete works
NRM 14 Masonry
Key considerations | 1 | 2 | 3 | 4 |
Preparation of an abstract for the proposed substructure work | ||||
Preparation a bill of quantities from the abstract including final quantities, referenced items of work, page totals and summary page |
Part 1 requires the transformation of the take off into the final BQ stage.
Top of Form
Bottom of Form
2) Based upon the drawings for the student accommodation used in unit 3 measure the suspended ceilings to all of the bedroom units excluding any work to the staircases and corridors including the preparation of an abstract and priced bill of quantities based on the specification and rates contained in the next paragraph.
Gyproc M/F suspended ceiling with hangers plugged and screwed to the concrete soffit, 900 x 1800 x 12.5mm tapered edge wallboard infill, joints filled with joint filler and taped to receive direct decoration. Rate £31.01 per m2
Decoration three coats emulsion paint. Rate £4.54 per m2
25 x 40mm softwood shadow gap to perimeters. Rate £3.80 per m
Decoration two coats black stain to exposed surface. £1.93 per m
- Sample take off paper and NRM for suspended ceilings and decorations included in reading material.
Key considerations | 1 | 2 | 3 | 4 |
Detailed measurement of the required work | ||||
Calculations of relevant areas and lengths including abstract of items | ||||
Preparation a bill of quantities from the abstract including final quantities, referenced items of work and page total |
Part 2 requires the proposed suspended ceiling works to be measured, abstracted, billed and priced.
Documents and drawings
5 Take off paper
NRM 29 Decoration
NRM 30 Suspended ceilings
100B Lower Ground Floor
101D Ground Floor
102D First Floor
103D Second Floor
104D Third Floor
105D Fourth Floor